During July actual labour costs amounted to 19,800, the standard rate of pay was 4.50 per hour and the labour rate variance amounted to 225 adverse. The actual hours worked were: |
A. | 4,400 |
B. | 1,012 |
C. | 4,350 |
D. | 3,450 |
Answer» A. 4,400 |