Q. |
Free float is mainly used to |
A. | Identify the activities which can be delayed without affecting the total float of preceding activity |
B. | Identify the activities, which can be delayed without affecting the total float of succeeding activity |
C. | Establish priorities |
D. | Identify the activities which can be delayed without affecting the total float of either the preceding or succeeding activities |
Answer» B. Identify the activities, which can be delayed without affecting the total float of succeeding activity |