If to, tp and tm are the optimistic, pessimistic and most likely time estimates of an activity respectively, the expected time t of the activity will be |
A. | to + 3tm+ tp/3 |
B. | to + 4tm+ tp/4 |
C. | to + 4tm+ tp/5 |
D. | to + 4tm+ tp/6 |
Answer» D. to + 4tm+ tp/6 |