Q. |
Suppose a project has many hazards that could easily injure one or more persons and there is no method of avoiding the potential for damages. The project manager should consider __________ as a means of deflecting the risk. |
A. | Abandoning the project |
B. | Buying insurance for personal bodily injury |
C. | Establishing a contingency fund |
D. | Establishing a management reserve |
Answer» B. Buying insurance for personal bodily injury |