The primary objective of cost-benefit analysis is |
A. | to find out direct and indirect cost of developing the information system |
B. | to determine the tangible benefits of the information system |
C. | to determine if it is economically worthwhile to invest in developing the information system |
D. | to determine the intangible benefits of the information system |
Answer» C. to determine if it is economically worthwhile to invest in developing the information system |