The land area required for installation of nuclear power plant is                  

A. more than thermal power plant
B. less than thermal power plant
C. equel to thermal power plant
D. depends on type of construction
Answer» C. equel to thermal power plant
Explanation: nuclear power plants need less area as compared to any other plant of same generation capacity. a 2000mw nuclear power plant needs about 80 acres whereas the