Q.

The purpose of earned value analysis is to

A. determine how to compensate developers based on their productivity
B. provide a quantitative means of assessing software project progress
C. provide a qualitative means of assessing software project progress
D. set the price point for a software product based on development effort
Answer» B. provide a quantitative means of assessing software project progress
Explanation: the purpose of earned value analysis is to provide a quantitative means of assessing software project progress