McqMate
401. |
Unavoidable cause of labour turnover is: |
A. | Low wages |
B. | Unsatisfactory working conditions |
C. | Long hours of work |
D. | Retrenchment due to shortage of work |
Answer» D. Retrenchment due to shortage of work |
402. |
Personal cause of labour turnover is: |
A. | Unfair method of promotion |
B. | Dislike for the job or place |
C. | Unsatisfactory working conditions |
D. | None of the above |
Answer» B. Dislike for the job or place |
403. |
Which of the following is a mechanical method of time keeping? |
A. | Time recording clock |
B. | Metal disc method |
C. | Attendance register method |
D. | None of the above |
Answer» A. Time recording clock |
404. |
Payment on the basis of the work done irrespective of the time taken by the worker is called: |
A. | Time rate system |
B. | Premium plan |
C. | Piece rate system |
D. | Bonus plan |
Answer» C. Piece rate system |
405. |
How many piece rates are set for each job in Taylor’s differential piece rate system? |
A. | Two |
B. | Three |
C. | Four |
D. | Many |
Answer» A. Two |
406. |
Overhead expenses can be classified according to |
A. | Functions |
B. | Elements |
C. | Behavior |
D. | All of the above |
Answer» D. All of the above |
407. |
The process of distribution of overheads allotted to a particular department or cost center over the units produced is called: |
A. | Allocation |
B. | Apportionment |
C. | Absorption |
D. | Departmentalization |
Answer» C. Absorption |
408. |
If an item of overhead expenditure is charged specifically to a single department this would be an example of: |
A. | Apportionment |
B. | Allocation |
C. | Re-apportionment |
D. | Absorption |
Answer» B. Allocation |
409. |
Example of semi-variable overhead items include the following except: |
A. | Telephone |
B. | Repairs and maintenance |
C. | Depreciation of plant and machinery |
D. | Insurance of plant and building |
Answer» D. Insurance of plant and building |
410. |
Which of the following costs is not a factory overhead expense? |
A. | Indirect wages |
B. | Depreciation of plant and machinery |
C. | Audit fees |
D. | Machine maintenance labour cost |
Answer» C. Audit fees |
411. |
The total of all indirect costs is known as |
A. | Total cost |
B. | Overhead |
C. | Prime cost |
D. | Work cost |
Answer» B. Overhead |
412. |
The bases of apportionment for electric power is |
A. | Number of machine hours |
B. | Floor area |
C. | Direct labour hours |
D. | Number of workers |
Answer» A. Number of machine hours |
413. |
When the amount of overhead absorbed is less than the amount of overhead incurred it is known as |
A. | Over-absorption |
B. | Under-absorption |
C. | Allocation |
D. | Apportionment |
Answer» B. Under-absorption |
414. |
Fixed overhead costs are also called as: - |
A. | Period cost |
B. | Flexible cost |
C. | Economic cost |
D. | Sunk cost |
Answer» A. Period cost |
415. |
Which materials do not normally form a past of finished goods: - |
A. | Indirect materials |
B. | Direct materials |
C. | Indirect labor |
D. | None of these |
Answer» A. Indirect materials |
416. |
Warehousing cost is an item of: - |
A. | Office overhead |
B. | Distribution overhead |
C. | Material cost |
D. | None of these |
Answer» B. Distribution overhead |
417. |
The excess of overheads absorbed over the actual amount of overheads incurred is called: - |
A. | Under absorption |
B. | Over absorption |
C. | Allocation |
D. | None of these |
Answer» B. Over absorption |
418. |
Lighting expenses are apportioned on the basis of: - |
A. | Floor Area |
B. | Light Points |
C. | No. of Workers |
D. | Capital Values |
Answer» B. Light Points |
419. |
Absorption costing is closely related to which of the following cost elements? |
A. | Total Costs |
B. | Overheads |
C. | Prime Costs |
D. | Direct labor |
Answer» B. Overheads |
420. |
To control costs it is essential to keep control on: - |
A. | Prime Cost |
B. | Overheads |
C. | Indirect materials |
D. | All of these |
Answer» D. All of these |
421. |
Which of the following is variable cost? |
A. | Salaries of higher officers |
B. | Prime cost |
C. | Insurance cost |
D. | Repair cost |
Answer» B. Prime cost |
422. |
Departmentalization of overhead is |
A. | Secondary distribution |
B. | Primary distribution |
C. | Absorption |
D. | Allocation |
Answer» B. Primary distribution |
423. |
Absorption means |
A. | Charging of overhead to cost centres |
B. | Charging if overhead to cost units |
C. | Charging of overhead to cost centres or units |
D. | None of the above |
Answer» C. Charging of overhead to cost centres or units |
424. |
A statement prepared to provide detailed cost of a cost centre or cost unit is |
A. | Cost account |
B. | Cost sheet |
C. | Reconciliation statement |
D. | Profit & loss a/c |
Answer» B. Cost sheet |
425. |
Over valuation of ________ in cost accounts is deducted to costing profit to find out financial profit. |
A. | Closing stock |
B. | Opening stock |
C. | Factory OH |
D. | Office OH |
Answer» A. Closing stock |
426. |
An aggregate of indirect material, indirect labourand indirect expenses is called |
A. | Capacity cost |
B. | Set-up cost |
C. | Depreciation |
D. | Overheads. |
Answer» D. Overheads. |
427. |
Production Manager’s salary is; |
A. | Factory overhead |
B. | Office overhead |
C. | Selling and distribution overheads |
D. | Administrative overhead |
Answer» A. Factory overhead |
428. |
Allotment of whole items of overheads to cost centres is known as; |
A. | allocation |
B. | apportionment |
C. | classification |
D. | absorption |
Answer» A. allocation |
429. |
Under absorption of overhead expense in cost accounting results in _______. |
A. | decrease in costing profit. |
B. | decrease in financial accounts profit |
C. | increase in costing profit |
D. | increase in financial accounts profit |
Answer» C. increase in costing profit |
430. |
The overheads which remain unaffected in total amount by fluctuations in volume of output. |
A. | Variable Overhead |
B. | Fixed Overhead |
C. | Semi-variable Overhead |
D. | None of the above |
Answer» B. Fixed Overhead |
431. |
Material costs which cannot be allocated but which are to be apportioned or absorbed by cost centres or cost units. |
A. | Direct Material |
B. | Indirect Material |
C. | Materials in progress |
D. | None of the above |
Answer» B. Indirect Material |
432. |
Certain overhead costs cannot be directly charged to a department or cost centres. The process of distribution of such overhead costs to various departments is called |
A. | Apportionment |
B. | Absorption |
C. | Allocation |
D. | None of the above |
Answer» A. Apportionment |
433. |
Rent and other building expenses may be apportioned to various departments on the basis of |
A. | Direct wages |
B. | Number of workers |
C. | Floor Area |
D. | Cost of Plant |
Answer» C. Floor Area |
434. |
The method of re-apportionment of overhead costs which is used when service department renders its services to other service departments but does not receive services of the other service departments. |
A. | Stepladder Method |
B. | Trial and Error Method |
C. | Repeated Distribution Method |
D. | All of the above |
Answer» A. Stepladder Method |
435. |
When the amount of overheads absorbed is less than the amount of overheads actually incurred. |
A. | Over absorption |
B. | Under Absorption |
C. | Excess Absorption |
D. | None of the above |
Answer» B. Under Absorption |
436. |
In case the amount of under or over absorbed overheads is significant, this rate is calculated to adjust the amount in the cost. |
A. | Additional rate |
B. | Secondary rate |
C. | Supplementary rate |
D. | Primary rate |
Answer» C. Supplementary rate |
437. |
When the under or over absorbed amount is quite negligible, it is transferred to |
A. | Costing P/L A/c |
B. | Costing Expenditure A/c |
C. | Costing Balance Sheet |
D. | Costing trading A/c |
Answer» A. Costing P/L A/c |
438. |
Classification of overheads into indirect material, indirect labour and indirect expenses come under: |
A. | Functional classification |
B. | Behaviour-wise classification |
C. | Nature-wise classification |
D. | Element-wise classification |
Answer» D. Element-wise classification |
439. |
Labour employed in time office and security office is an example of: |
A. | Direct labour |
B. | Indirect labour |
C. | Indirect expenses |
D. | Direct expenses |
Answer» B. Indirect labour |
440. |
Depreciation of plant and machinery is apportioned on the basis of: |
A. | Technical estimates |
B. | Direct labour hours |
C. | Kilowatt hours |
D. | Capital value of assets |
Answer» D. Capital value of assets |
441. |
Supervision is charged on the basis of: |
A. | Number of employees |
B. | Direct material |
C. | Direct wages |
D. | Area of department |
Answer» A. Number of employees |
442. |
Power charges are: |
A. | Fixed overhead |
B. | Variable overhead |
C. | Semi-variable overhead |
D. | Semi-fixed overhead |
Answer» B. Variable overhead |
443. |
Overheads classified as Manufacturing, Administrative, Selling and Distribution come under: |
A. | Function-wise classification |
B. | Element-wise classification |
C. | Behavior-wise classification |
D. | Industry-wise classification |
Answer» A. Function-wise classification |
444. |
Depreciation of office equipments is an example of: |
A. | Factory overheads |
B. | Administrative overheads |
C. | Selling overheads |
D. | Manufacturing overheads |
Answer» B. Administrative overheads |
445. |
Allotment of overhead to a cost unit is called: |
A. | Apportionment |
B. | Absorption |
C. | Allocation |
D. | Departmentation |
Answer» B. Absorption |
446. |
In ________ costing the cost of a group of products is ascertained. |
A. | Process |
B. | Job |
C. | Batch |
D. | Service |
Answer» C. Batch |
447. |
________ costing is suitable for mines, quarries, cement works etc. |
A. | Process |
B. | Contract |
C. | Batch |
D. | Operation |
Answer» D. Operation |
448. |
________ is an extension of job costing. |
A. | Process costing |
B. | Batch costing |
C. | Contract costing |
D. | Operation costing |
Answer» B. Batch costing |
449. |
When job is very big and spread over long periods of time the method of costing adopted is |
A. | Process |
B. | Job |
C. | Contract |
D. | Batch |
Answer» C. Contract |
450. |
Continuous costing is also called |
A. | Operation costing |
B. | Process costing |
C. | Batch costing |
D. | Contract costing |
Answer» B. Process costing |
451. |
In this type of costing works are carried out at factory premises: |
A. | Job |
B. | Contract |
C. | Batch |
D. | Process |
Answer» A. Job |
452. |
Under this method, homogeneous products are taken as cost unit |
A. | Job |
B. | Contract |
C. | Batch |
D. | Process |
Answer» C. Batch |
453. |
The costing method which can be used in industry where the product passes through different processes is known as |
A. | Job costing |
B. | Operating costing |
C. | Batch costing |
D. | Process costing |
Answer» D. Process costing |
454. |
Under which method costs are collected & accumulated for each job: - |
A. | Job Costing |
B. | Contract Costing |
C. | Batch Costing |
D. | None of these |
Answer» A. Job Costing |
455. |
The basis of collection of costs are:- |
A. | Materials |
B. | Wages |
C. | Overheads |
D. | All of these |
Answer» D. All of these |
456. |
Which method is adopted to calculate the cost of each batch? |
A. | Contract Costing |
B. | Job Costing |
C. | Batch Costing |
D. | Job sheet |
Answer» C. Batch Costing |
457. |
In what basis of work, the contractor is made payment? |
A. | Certified Work |
B. | Uncertified Work |
C. | National Profit |
D. | None of these |
Answer» A. Certified Work |
458. |
Ascertainment of cost of the product at each process is called: - |
A. | Job Costing |
B. | Contract Costing |
C. | Process Costing |
D. | Batch Costing |
Answer» C. Process Costing |
459. |
A contract account is a _______ account in nature. |
A. | Real a/c |
B. | Personal a/c |
C. | Nominal a/c |
D. | All of these |
Answer» C. Nominal a/c |
460. |
Identify the types of specific order costing. |
A. | Job Costing |
B. | Batch Costing |
C. | Both (a) & (b) |
D. | Process Costing |
Answer» C. Both (a) & (b) |
461. |
Which of the following is known as Terminal Costing? |
A. | Job Costing |
B. | Batch Costing |
C. | Process Costing |
D. | Contract Costing |
Answer» D. Contract Costing |
462. |
The costing method which can be used in industry where the product pass through different processes is known as______. |
A. | job costing |
B. | operating costing |
C. | batch costing |
D. | process costing |
Answer» D. process costing |
463. |
Process Account is _____. |
A. | Nominal A/c |
B. | Real A/c |
C. | Personal A/c |
D. | either Nominal or Real A/c |
Answer» A. Nominal A/c |
464. |
Profit to be transferred to P& L A/c , if the contract is complete to the extent of only 20% is _____. |
A. | nil |
B. | 20% |
C. | 25% |
D. | 75% |
Answer» A. nil |
465. |
If the actual loss is more than the estimated normal loss, then it is |
A. | abnormal loss |
B. | normal loss |
C. | seasonal loss |
D. | abnormal gain |
Answer» A. abnormal loss |
466. |
The sum of value of work certified and uncertified appearing in the Contract Account is called |
A. | Work in Progress |
B. | Work in Process |
C. | Work completed |
D. | Work done |
Answer» A. Work in Progress |
467. |
Contract costing is specialized system of job costing applies to _____ contracts. |
A. | Short-term |
B. | Medium-term |
C. | Long-term |
D. | Continuous process |
Answer» C. Long-term |
468. |
Each job has a ______ prepare for it that bears the job number and which is used to collect all cost data relating to job. |
A. | Job time sheet |
B. | Job Cost Card |
C. | Job ticket |
D. | Job Account |
Answer» B. Job Cost Card |
469. |
The first step in a job order cost procedure is |
A. | Receiving of order |
B. | Estimation of the price of the job |
C. | Production order |
D. | Receiving an enquiry |
Answer» D. Receiving an enquiry |
470. |
Job Costing is suitable for |
A. | Ship-builders |
B. | Furniture makers |
C. | Printing presses |
D. | All of the above |
Answer» D. All of the above |
471. |
Batch costing is a form of specific order/job costing where the cost per unit is ascertained by _________ the total cost of a batch by the number of items produced in that batch. |
A. | dividing |
B. | multiplying |
C. | subtracting |
D. | adding |
Answer» D. adding |
472. |
The determination of EBQ is influenced by the following factors: |
A. | Rate of consumption |
B. | Manufacturing cost |
C. | Storage cost |
D. | All of the above |
Answer» D. All of the above |
473. |
Work which has been done but not certified is called |
A. | Work uncertified |
B. | Work certified |
C. | Extra work |
D. | None of the above |
Answer» A. Work uncertified |
474. |
The sum of value of work certified and uncertified appearing in the contract account is called |
A. | Work in process |
B. | Work completed |
C. | Work in progress |
D. | None of the above |
Answer» A. Work in process |
475. |
Loss which unavoidable on account of inherent nature of production processes is |
A. | Abnormal loss |
B. | Normal loss |
C. | Process loss |
D. | None of the above |
Answer» B. Normal loss |
476. |
In process costing when the actual loss is less than the normal loss then it is |
A. | Abnormal gain |
B. | Abnormal loss |
C. | Process gain |
D. | None of the above |
Answer» A. Abnormal gain |
477. |
What we prepare for each job that bears the job number and which is used to collect all cost data relating to job is: |
A. | Job time sheet |
B. | Job cost card |
C. | Job ticket |
D. | Job account |
Answer» B. Job cost card |
478. |
An automobile service unit uses: |
A. | Batch costing |
B. | Contract costing |
C. | Job |
D. | Specific order |
Answer» B. Contract costing |
479. |
Where the work is undertaken to customer’s special requirements and each order is of comparatively short duration, then it is called: |
A. | Job costing |
B. | Batch costing |
C. | Operation costing |
D. | Output costing |
Answer» A. Job costing |
480. |
Printing industry uses: |
A. | Job costing |
B. | Batch costing |
C. | Operation costing |
D. | Output costing |
Answer» B. Batch costing |
481. |
Batch costing is a form of: |
A. | Process costing |
B. | Continuous process costing |
C. | Specific order costing |
D. | Operation costing |
Answer» C. Specific order costing |
482. |
Batch costing is applied in: |
A. | Pharmaceutical industries |
B. | Computer industries |
C. | Toy making |
D. | All of the above |
Answer» D. All of the above |
483. |
Batch costing is used for which type of product? |
A. | Heterogeneous product |
B. | By-product |
C. | Homogeneous product |
D. | All of the above |
Answer» C. Homogeneous product |
484. |
Contract costing is a specialized system of Job costing applies to: |
A. | Short term contracts |
B. | Medium term contracts |
C. | Long term contracts |
D. | Continuous process |
Answer» C. Long term contracts |
Done Reading?