McqMate
1. |
Process of maintaining different components of building so that it can provide proper service throughout its working life is known as__________ |
A. | Building maintenance |
B. | Building management |
C. | Building service |
D. | Building repairs |
Answer» A. Building maintenance |
2. |
Which type of activity is carried out during the maintenance process? |
A. | Repair of plaster |
B. | Repair of cracks in walls and ceiling |
C. | Repair of flooring settlement |
D. | All of the above |
Answer» D. All of the above |
3. |
Which type of plaster defect generates a swelling in plaster surface? |
A. | Crazing |
B. | Blistering |
C. | Flaking |
D. | Popping |
Answer» B. Blistering |
4. |
Which type of plaster defect generates a series of hair cracks inside the plaster? |
A. | Crazing |
B. | Blistering |
C. | Flaking |
D. | Popping |
Answer» A. Crazing |
5. |
Which type of chemical is used for the anti-termite treatment of the soil? |
A. | Aldrin |
B. | Haptachlor |
C. | A & B both |
D. | None of the above |
Answer» C. A & B both |
6. |
Which type of maintenance work is taken to prevent a wear or decay of building? |
A. | Preventive maintenance |
B. | Remedial maintenance |
C. | Day to day maintenance |
D. | Special maintenance |
Answer» A. Preventive maintenance |
7. |
Which type of maintenance is known as a preventive maintenance? |
A. | Routine maintenance |
B. | Periodical maintenance |
C. | Pre & pose monsoon maintenance |
D. | All of the above |
Answer» D. All of the above |
8. |
Simplest method of identifying weak spots are_______ |
A. | visual inspection |
B. | tapping the surface |
C. | chipping the weak concrete |
D. | both a & b |
Answer» D. both a & b |
9. |
Mortar or concrete conveyed through pressure hose and applied pneumatically at high velocity on to a surface is called |
A. | guniting |
B. | grouting |
C. | sealing |
D. | spraying |
Answer» A. guniting |
10. |
Which type of work is done in day to day repair? |
A. | Remove chokage in pipes |
B. | Cleaning of manholes |
C. | Lawn moving |
D. | All of the above |
Answer» D. All of the above |
11. |
White washing is done during________ |
A. | Annual repair |
B. | Day to day repair |
C. | Special repair |
D. | Major repair |
Answer» A. Annual repair |
12. |
In which type of repair major concreting work is carried out? |
A. | Annual repair |
B. | Day to day repair |
C. | Special repair |
D. | Major repair |
Answer» C. Special repair |
13. |
A big crack is observed in the C I water mains suitable remedy is to |
A. | paint the crack with bitumen paint |
B. | use rich cement plaster to cover the crack |
C. | provide clamps to cover the crack |
D. | cut affected pipe length and replace it with another pipe |
Answer» D. cut affected pipe length and replace it with another pipe |
14. |
Honey combing is caused due to |
A. | inadequate compaction |
B. | chemical reaction |
C. | shock waves |
D. | lack of curing |
Answer» A. inadequate compaction |
15. |
Drying shrinkage can be reduced by__________ |
A. | using practical amount of aggregate |
B. | lowest usable water content |
C. | using shrinkage compensating cement |
D. | all the above |
Answer» D. all the above |
16. |
Payment of annual repair is given based on the_________ |
A. | work quality |
B. | work quantity |
C. | no. of required workers |
D. | location of the site |
Answer» A. work quality |
17. |
In general, electric wiring of the buildings are change at every ________ year. |
A. | 15-20 |
B. | 20-30 |
C. | 20-25 |
D. | 30-45 |
Answer» C. 20-25 |
18. |
Adding water to improve workability has the effect of_________ |
A. | reducing strength |
B. | increasing settlement |
C. | drying shrinkage |
D. | all the above |
Answer» D. all the above |
19. |
Which factors kept in mind during the building survey of the buildings? |
A. | time of last inspection |
B. | Who inspect the building? |
C. | level of deterioration in building parts |
D. | all of the above |
Answer» D. all of the above |
20. |
Moisture and temperature on timber causes |
A. | dimensional changes |
B. | shape changes |
C. | mould growth |
D. | all the above |
Answer» D. all the above |
21. |
Fungi are minute microscopic plant organism. They attack timber in the following condition |
A. | the moisture content in timber is above 20% |
B. | there is presence of air and warmth for the growth of fungi |
C. | the timber is continuously soaked in water |
D. | both a & b |
Answer» D. both a & b |
22. |
Which of the following materials can you use for checking minor leakages through CI pipe joints? |
A. | white lead. |
B. | cement |
C. | lead wool |
D. | grease |
Answer» C. lead wool |
23. |
Decay of timber may be caused by certain insects |
A. | beetles |
B. | marine borers |
C. | white ants |
D. | all the above |
Answer» D. all the above |
24. |
There is seepage of water on both sides of load bearing wall of a building with flat roof. What remedy will you suggest? |
A. | Remove plaster on the wall and replaster with rich mix. |
B. | Inspect the roof for cracks over the wall and seal the crack. |
C. | Paint both the surfaces of the wall with oil paint. |
D. | Plaster both the surface of wall with cement mortar mixed with water proofing compound. |
Answer» B. Inspect the roof for cracks over the wall and seal the crack. |
25. |
Which of the following is not a anti-termite Measure to protect wood work are |
A. | use only wood that is naturally durable |
B. | no under moisture accumulation about susceptible |
C. | painting of timber structures |
D. | creating poisoned soil |
Answer» C. painting of timber structures |
26. |
According to the CPWD guideline, schedule for the annual maintenance work should be complete on or before_______ |
A. | 30th April |
B. | 31st January |
C. | 15th August |
D. | 1st March |
Answer» A. 30th April |
27. |
Termite make the timber |
A. | crack |
B. | porous |
C. | moist |
D. | wet and dry rot |
Answer» B. porous |
28. |
Which chemical is used for the removal of the fungus? |
A. | ammoniac copper solution |
B. | a & c |
C. | magnesium fluoride |
D. | none of the above |
Answer» B. a & c |
29. |
How much amount of sodium pentachlorophenates is used for fungus removal compound? |
A. | 2% |
B. | 2.5% |
C. | 3.5% |
D. | 5% |
Answer» A. 2% |
30. |
Code for painting on a concrete, masonry & plaster surface are given in ___________ |
A. | IS : 2395 :1994 |
B. | IS : 2399 :1994 |
C. | IS : 2396 :1994 |
D. | IS : 2395 :1995 |
Answer» A. IS : 2395 :1994 |
31. |
Deflection was noticed in a newly constructed properly designed R.C.C.beam. The defect may be due to____________ |
A. | very longs pan. |
B. | diagonal cracks near edge of support |
C. | insufficient concrete cover. |
D. | early removal of form work. |
Answer» D. early removal of form work. |
32. |
Most suitable method of protecting steel columns of a multistoried building against rusting is to: |
A. | paint with aluminium paint. |
B. | paint with bitumen paint. |
C. | paint with redoxide. |
D. | encase in concrete |
Answer» A. paint with aluminium paint. |
33. |
Which one of the following methods will be the best method to make R.C.C slab leak proof? |
A. | Plaster the roof with cement mortar |
B. | Lime koba layer over R.C roof with proper slopes |
C. | soap solution to be sprinkled over the R.C roof |
D. | Bitumen paint on whole roof surface |
Answer» B. Lime koba layer over R.C roof with proper slopes |
34. |
Which one the following is used to protect the steel from rusting |
A. | Zinc oxide |
B. | White lead |
C. | Molten lead |
D. | Red lead |
Answer» D. Red lead |
35. |
The most appropriate cement for reparing cracks in R.C.C works is. |
A. | Port land cement |
B. | Expansive cement |
C. | Quick setting cement |
D. | Low heat cement |
Answer» C. Quick setting cement |
36. |
Steel structure is likely to come in contact with water. To prevent rusting. |
A. | Apply bitumen coat |
B. | Apply anti corrosive paint |
C. | varnish paint |
D. | slacked lime coat |
Answer» B. Apply anti corrosive paint |
37. |
The most effective method of removing old paint from structure is______ |
A. | Washing with water |
B. | Scrubbing with gunny bag |
C. | Use of oxy-acetylene flame |
D. | Polishing with grinding stone |
Answer» B. Scrubbing with gunny bag |
38. |
Which type of paint affect generates, when water vapor is trapped inside paint? |
A. | Peeling |
B. | Blistering |
C. | Cracking |
D. | Flaking |
Answer» B. Blistering |
39. |
If paint is poor in adhesion than it causes_________. |
A. | Peeling |
B. | Blistering |
C. | Cracking |
D. | Flaking |
Answer» D. Flaking |
40. |
Creaking inside paint generates due to __________. |
A. | excessive use of putty |
B. | very thick coat of the paint |
C. | crack in plaster |
D. | All of the above |
Answer» D. All of the above |
41. |
Applying paint under high humidity causes ______________. |
A. | Blooming |
B. | Pin holes |
C. | Cracking |
D. | none of the above |
Answer» A. Blooming |
42. |
In a brick masonry structure the following defects are noticed during inspection. Which one of them requires immediate maintenance repair? |
A. | Dampness on wall |
B. | Growth of vegetation |
C. | Structure failure by settlement |
D. | Falling of plaster |
Answer» C. Structure failure by settlement |
43. |
Which type of paint is used for plaster walls? |
A. | while washing |
B. | Cement paints |
C. | Dry distemper |
D. | all of the above |
Answer» D. all of the above |
44. |
Paint for the white washing is made by__________. |
A. | lime and water |
B. | cement and water |
C. | oil and cement |
D. | oil and epoxy |
Answer» A. lime and water |
45. |
Which paint is made by the powder chalk? |
A. | while washing |
B. | Cement paints |
C. | Dry distemper |
D. | oil bound paint |
Answer» C. Dry distemper |
46. |
Filler coat is applies over a _________. |
A. | prime coat |
B. | final coat |
C. | paint coat |
D. | finishing coat |
Answer» A. prime coat |
47. |
Which type of paint allows a free movement of the air through its layer? |
A. | non-breathing paints |
B. | breathing paints |
C. | plastic paints |
D. | none of the above |
Answer» B. breathing paints |
48. |
Interior walls of a building have developed cracks. Remedial measures adopted will be to |
A. | Fill cracks by port land cement mortar |
B. | Fill cracks with bitumen. |
C. | Use expansive cement mortar for filling cracks. |
D. | Use water proofing compound to fill cracks |
Answer» A. Fill cracks by port land cement mortar |
49. |
The main aim of maintaining any structures is to |
A. | Improve its appearance |
B. | Utilize the funds provided |
C. | Stabilize the structure so as to enable it carry the functions for which it is constructed |
D. | Utilize services of in charge maintenance |
Answer» C. Stabilize the structure so as to enable it carry the functions for which it is constructed |
50. |
Which of the following jobs will you classify as special maintenance |
A. | Replacing door frame damaged by white ants |
B. | Renewal coat to W.B.M road surface |
C. | White washing and colour washing of buildings |
D. | Painting of steel roof trusses of a workshop |
Answer» B. Renewal coat to W.B.M road surface |
51. |
The high pH of the fresh concrete make a thin oxide film around the reinforcement steel |
A. | true |
B. | false |
C. | none |
D. | all |
Answer» A. true |
52. |
The pH value of fresh concrete is around |
A. | 10 |
B. | 11 |
C. | 11.5 |
D. | 12.5 |
Answer» D. 12.5 |
53. |
If the cracks width is less than 0.1 mm then they are called |
A. | fine |
B. | thin |
C. | medium |
D. | wide |
Answer» A. fine |
54. |
Surface coating is also one of the methods of treating cracks. |
A. | true |
B. | false |
C. | none |
D. | all |
Answer» A. true |
55. |
Painting work should be start after 3 to 6 month of plastering on new walls. |
A. | true |
B. | false |
C. | none |
D. | all |
Answer» A. true |
56. |
How much time required for curing of cement paints? |
A. | 2 – 3 hr |
B. | 4 – 10 hr |
C. | 6 – 7 hr |
D. | 1 – 2 hr |
Answer» B. 4 – 10 hr |
57. |
Use of electricity is measured in ____________ for home electric system. |
A. | V |
B. | W |
C. | kWh |
D. | mA |
Answer» C. kWh |
58. |
How much load is acceptable on one circuit in home electric system? |
A. | 4 KW |
B. | 5 KW |
C. | 3 KW |
D. | 10 KW |
Answer» C. 3 KW |
59. |
How much maximum current is allow in single circuit for home electric system? |
A. | 20A |
B. | 10A |
C. | 25A |
D. | 15A |
Answer» D. 15A |
60. |
What is functions of home water supply system? |
A. | to provide a fresh water |
B. | distribute the water thought out a home |
C. | store the water inside the home |
D. | all of the above |
Answer» D. all of the above |
61. |
Flushing is one of the method of cleaning |
A. | water pipe |
B. | sewer pipe |
C. | steam pipe |
D. | drain pipe |
Answer» B. sewer pipe |
62. |
The approaches made for inspection & cleaning of sewers is called |
A. | trap |
B. | cover |
C. | manhole |
D. | drain |
Answer» C. manhole |
63. |
The process of supplying fresh air into a closed space for removal of foul smell is called |
A. | airing |
B. | venting |
C. | proving |
D. | ventilation |
Answer» D. ventilation |
64. |
Ventilation depends on |
A. | humidity |
B. | temperature |
C. | air change |
D. | all of the above |
Answer» D. all of the above |
65. |
Stains caused by paints & varnish can be removed by |
A. | carbon tetrachloride |
B. | water |
C. | oil |
D. | grease |
Answer» A. carbon tetrachloride |
66. |
While preparing the maintenance estimate the capital cost of building is deducted. |
A. | true |
B. | false |
C. | none |
D. | all |
Answer» A. true |
67. |
Maintaining prestressed concrete structures of various types in a fit and serviceable condition is primary function of ____________ |
A. | Maintenance engineer |
B. | Design engineer |
C. | Surface engineer |
D. | Structural engineer |
Answer» A. Maintenance engineer |
68. |
The structural concrete slab panels can be repaired by ____________ |
A. | Internal bonding |
B. | External bonding |
C. | Stress bonding |
D. | Layered bonding |
Answer» B. External bonding |
69. |
Blistering and peeling is one of the defect seen in |
A. | concrete |
B. | walling |
C. | painting |
D. | plumbing |
Answer» C. painting |
70. |
Rehabilitation of structures may be required due to several reasons. Choose the correct reason. |
A. | Environmental effects |
B. | Tensile effects |
C. | Compressive effects |
D. | Range effects |
Answer» A. Environmental effects |
71. |
What is the problem of rehabilitation? |
A. | Unique |
B. | Submerged |
C. | Lined |
D. | Layered |
Answer» A. Unique |
72. |
The repair and rehabilitation of damaged or spelled concrete is done by removing the _____ |
A. | Loose concrete |
B. | Collapsing |
C. | Breakage |
D. | Bonding |
Answer» A. Loose concrete |
73. |
In restoration of strength by adding external reinforced concrete the damages concrete is first repaired by applying ____________ |
A. | Preload |
B. | Tensile load |
C. | Compressive load |
D. | Overload |
Answer» A. Preload |
74. |
The corrosion of reinforcement due to extreme exposure is common for structure located in _ |
A. | Dry conditions |
B. | Costal zones |
C. | Regional zones |
D. | Hot condition |
Answer» B. Costal zones |
75. |
The repair procedure in severe damage includes ____________ |
A. | Grouting |
B. | Collapse |
C. | Shortcrete |
D. | Mud |
Answer» C. Shortcrete |
76. |
Which pipe is used for carrying a human waste? |
A. | soil pipe |
B. | vent pipe |
C. | waste pipe |
D. | rainwater pipe |
Answer» A. soil pipe |
77. |
Which pipe is used for maintain a ventilation is sewage system? |
A. | soil pipe |
B. | vent pipe |
C. | anti-siphonage pipe |
D. | rainwater pipe |
Answer» C. anti-siphonage pipe |
78. |
Main causes of failure of the structure? |
A. | design error |
B. | materials |
C. | inspection |
D. | all of the above |
Answer» D. all of the above |
79. |
What is unpredictable factors of failure of structure? |
A. | earthquake |
B. | bomb blast |
C. | natural disaster |
D. | all of the above |
Answer» D. all of the above |
80. |
What is main causes of horizontal cracks in concrete? |
A. | plastic shrinkage |
B. | settlement cracking |
C. | early removal of the formwork |
D. | all of the above |
Answer» A. plastic shrinkage |
81. |
Causes of distress of concrete is _____ |
A. | high load |
B. | accident |
C. | corrosion |
D. | all of the above |
Answer» D. all of the above |
82. |
In how many layers is oil paint applied to a surface? |
A. | 3 |
B. | 4 |
C. | 2 |
D. | 1 |
Answer» A. 3 |
83. |
Emulsion Paints contain: |
A. | Nitro cotton |
B. | Zinc white |
C. | White lead |
D. | Polyvinyl acetate |
Answer» D. Polyvinyl acetate |
84. |
Anticorrosive paint is ___________ in color |
A. | Blue |
B. | White |
C. | Black |
D. | Yellow |
Answer» B. White |
85. |
In which of the below, it is not necessary to remove existing paint to apply a new one? |
A. | Aluminum paints |
B. | Cement paints |
C. | Oil paints |
D. | Enamel paints |
Answer» C. Oil paints |
86. |
Synthetic rubber paints are prepared from: |
A. | Resin |
B. | Rubber |
C. | Synthetic fibers |
D. | Polyvinyl Chloride |
Answer» A. Resin |
87. |
What is used to make paints odorless to an extent? |
A. | Flat latex |
B. | Celluloid sheets |
C. | Acrylic compound |
D. | Plioway resins |
Answer» D. Plioway resins |
88. |
Spray painting is used to: |
A. | Apply paint without touching surface |
B. | Apply large amount of paint |
C. | Reach high areas |
D. | Get textured paint |
Answer» A. Apply paint without touching surface |
89. |
At roof slab level over the DPC, __________ are provided. |
A. | Tiles |
B. | Concrete |
C. | P.C.C |
D. | Rubber sheet |
Answer» A. Tiles |
90. |
DPM stands for: |
A. | Damp Proof Material |
B. | Damp Proof Mix |
C. | Damp Proof Member |
D. | Damp Proof Membrane |
Answer» D. Damp Proof Membrane |
91. |
Which of the below is an example of semi rigid DPC material? |
A. | Plastic sheeting |
B. | Cement concrete |
C. | Asphalt |
D. | Stone |
Answer» C. Asphalt |
92. |
For DPC at plinth level, which grade of concrete is used? |
A. | M10 |
B. | M20 |
C. | M25 |
D. | M15 |
Answer» D. M15 |
93. |
In a white wash, after how many hours is dissolved gum added to the solution? |
A. | 24 hours |
B. | 12 hours |
C. | 6 hours |
D. | 1 hour |
Answer» A. 24 hours |
94. |
The appearance of glossy patches on the painted surface is called: |
A. | Flashing |
B. | Blooming |
C. | Running |
D. | Blistering |
Answer» A. Flashing |
95. |
Which document used for note down the data during the structure assessments? |
A. | work sheet |
B. | site book |
C. | work book |
D. | data book |
Answer» A. work sheet |
96. |
There are _____ stages in condition survey. |
A. | 5 |
B. | 4 |
C. | 3 |
D. | 2 |
Answer» B. 4 |
97. |
Which test used for identifying the corrosion in RCC beam? |
A. | resistivity test |
B. | Halfcell potential |
C. | a & b both |
D. | none of the above |
Answer» C. a & b both |
98. |
Which test used for identifying the integrity of RCC beam? |
A. | tapping |
B. | pulse-echo |
C. | radar test |
D. | all of the above |
Answer» D. all of the above |
99. |
Wood surface requires _________ coats of plastering. |
A. | 2 |
B. | 3 |
C. | 1 |
D. | none of the above |
Answer» B. 3 |
100. |
Which admixture is used to improve workability? |
A. | Plasticizers |
B. | Metakaolin |
C. | Reducers |
D. | Accelerators |
Answer» A. Plasticizers |
Done Reading?