Choose the correct statement. |
| A. | CPM and PERT are event oriented techniques |
| B. | CPM and PERT are activity oriented techniques |
| C. | CPM is an activity oriented technique while PERT is an event oriented technique |
| D. | None of the above |
| E. | Supply and demand conditions |
| Answer» C. CPM is an activity oriented technique while PERT is an event oriented technique | |