A. | it defines tasks required to define resources, timelines, and other project related information |
B. | it defines a set of negotiation activities at the beginning of each pass around the spiral |
C. | it defines tasks required to assess both technical and management risks |
D. | it defines tasks required to construct, test, install, and provide user support |
Answer» B. it defines a set of negotiation activities at the beginning of each pass around the spiral | |
Explanation: except option “b” all other tasks/activities are present in spiral model as well. |