How is WINWIN Spiral Model different from Spiral Model? |
| A. | it defines tasks required to define resources, timelines, and other project related information |
| B. | it defines a set of negotiation activities at the beginning of each pass around the spiral |
| C. | it defines tasks required to assess both technical and management risks |
| D. | it defines tasks required to construct, test, install, and provide user support |
| Answer» B. it defines a set of negotiation activities at the beginning of each pass around the spiral | |
| Explanation: except option “b” all other tasks/activities are present in spiral model as well. | |