Q. |
Which of the following is not a part of process change? |
A. | introducing new practices, methods or processes |
B. | introducing new team members to existing project |
C. | introducing or removing deliverable |
D. | introducing new roles or responsibilities |
Answer» B. introducing new team members to existing project | |
Explanation: adding more developers aid to process completion rather than changing it. |