Q.

In a factory Standard rate per hour Rs. 4, Standard time per unit of output – 20 hours, Units produced - 500, Actual hours worked - 12,000. Compute Labour Efficiency Variance.

A. Rs. 6000 (Favourable)
B. Rs. 8000 (Adverse)
C. Rs. 9,600 (Favourable)
D. Rs. 8000 (Favourable)
Answer» B. Rs. 8000 (Adverse)