Earliest finish time can be regarded as |
A. | Earliest start time + duration of activity |
B. | Earliest start time duration of activity |
C. | Latest finish time + duration of activity |
D. | Latest finish time duration of activity |
Answer» A. Earliest start time + duration of activity |