Which of the following is not a tool and technique used in the process of Plan Risk Responses |
A. | Contingent Response Strategies |
B. | Expert Judgment |
C. | Risk and Impact Matrix |
D. | Strategies for positive risks or opportunities |
Answer» C. Risk and Impact Matrix |