During which stage of Risk planning are modeling techniques used to determine overall effects of risks on project objectives for high probability, high impact risks? |
A. | Identify Risks |
B. | Plan Risk responses |
C. | Perform Qualitative risk analysis |
D. | Perform Quantitative risk analysis |
Answer» D. Perform Quantitative risk analysis |