Q. |
Following are the phases of Project Management Life Cycle. Arrange them in correct order Design, 2. Marketing, 3. Analysis and evaluation, 4. Inspection, testing and delivery |
A. | 3-2-1-4 |
B. | 1-2-3-4 |
C. | 2-3-1-4 |
D. | 4-3-2-1 |
Answer» A. 3-2-1-4 |