Q.

In the case of works which require some special types of equipment, an amount of

A. 1-2
B. 5-9
C. 12-18
D. 16-20
Answer» A. 1-2
Explanation: in the case of works that require some special types of equipment, an amount of 1-2 percent of the estimated cost is given. while preparing a detailed estimate, it is also important to select a suitable site of work to reduce damage during the loading and unloading of materials.