In the case of works which require some special types of equipment, an amount of |
| A. | 1-2 |
| B. | 5-9 |
| C. | 12-18 |
| D. | 16-20 |
| Answer» A. 1-2 | |
| Explanation: in the case of works that require some special types of equipment, an amount of 1-2 percent of the estimated cost is given. while preparing a detailed estimate, it is also important to select a suitable site of work to reduce damage during the loading and unloading of materials. | |