Q.

                                 is the amount provided in the estimate and bill of quantities for some specialised work to be done by a specialised firm; whose details are not known at the time of preparing estimate.

A. prime cost
B. provisional sum
C. capital cost
D. building cost index
Answer» B. provisional sum