Q.

In case the probability factor is zero, it can be concluded that

A. the project is bound to fail
B. the chances of completion of the project are 100%
C. the chances of completion of the project are 50%
D. the chances of completion of the project are less than 50%.
E. None of the above
Answer» C. the chances of completion of the project are 50%
2k
0
Do you find this helpful?
19

View all MCQs in

Industrial Engineering

Discussion

No comments yet