![Mcqmate logo](https://mcqmate.com/public/images/logos/logo-black.png)
![Mcqmate logo](https://mcqmate.com/public/images/logos/logo-white.png)
McqMate
Q. |
The irreducible minimum duration of the project is called______. |
A. | critical time |
B. | crashed duration |
C. | cost slope |
D. | crash cost |
Answer» B. crashed duration |
View all MCQs in
Computer Aided Optimisation TechniquesNo comments yet