Which of the following paradigm attempts to structure a team in a manner that achieves some of the controls associated with the closed paradigm but also much of the innovation that occurs when using the random paradigm? |
| A. | asynchronous paradigm |
| B. | open paradigm |
| C. | closed paradigm |
| D. | synchronous paradigm |
| Answer» B. open paradigm | |
| Explanation: open paradigm team structures are well suited to the solution of complex problems but may not perform as efficiently as other teams. | |