Q.

Effective release time of a job with predecessors is equal to the maximum value among, its…………and…………..

A. deadline time and effective release time of all of the predecessors.
B. release time and effective release time of all of the predecessors.
C. both
D. None of these
Answer» B. release time and effective release time of all of the predecessors.