Q.

You have just completed Qualitative Risk Analysis of the project. What should you be doing next?

A. Plan Risk Management
B. Perform Quantitative Risk Analysis
C. Plan Risk Responses
D. Control Risks
Answer» B. Perform Quantitative Risk Analysis