

McqMate
Q. |
Who has ultimate responsibility for project risk? |
A. | Steering group. |
B. | Risk owner. |
C. | Project sponsor. |
D. | Project manager. |
Answer» C. Project sponsor. |
View all MCQs in
Project ManagementNo comments yet