Q.

The firm’s direct-labour rate variance was 4,800 unfavourable. Actual labour was 24,000 direct-labour hours, at a cost of 1,68,000, for 25,000 units of finished product that require 1 hour of direct labour each, at standard. What is the standard rate per direct-labour hour?

A. 7.20
B. 6.80
C. 7.00
D. Cannot be determined from the information given
Answer» D. Cannot be determined from the information given