Q.

To produce a particular batch of product, Falcon Corporation paid its workers 12.00 per hour for 4,000 hours of work. The standards for the quantity of work represented by the batch were 12.50 per hour and 4,400 hours. What was the labour efficiency variance?

A. 2,000.00 favourable
B. 5,000.00 favourable
C. 5,000.00 unfavourable
D. None of these
Answer» B. 5,000.00 favourable