Q.

Plan-do-study-act cycle is a procedure to

A. overall improvement
B. continuous improvement
C. permanent improvement
D. immediate improvement
Answer» B. continuous improvement
Explanation: pdsa cycle is an iterative four-step management method used in business for the control and continuous improvement of processes and products
so option b is correct.