Consider that for a particular process, the p has shifted to .4 and the process has gone out of control. The corresponding value of beta is found to be .3356. The value of Average Run Length is: |
A. | 2.5 |
B. | 1.5 ((1/1-beta) provides us with average run length) |
C. | 1.0 |
D. | 2.7 |
Answer» B. 1.5 ((1/1-beta) provides us with average run length) |