In Basic execution time model, additional number of failures required to achieve a failure intensity objective is expressed as |
A. | 0/λ0(λP - λF) |
B. | ) 0/λ0(λF – λP) |
C. | λ0 0(λF – λP) |
D. | λ0/ 0 (λP - λF) |
Answer» A. 0/λ0(λP - λF) |