Q.

If project A has a lower payback period than project B, this may indicate that project A may have a …………….

A. Lower NPV and be less profitable
B. Higher NPV and be less profitable
C. Higher NPV and be more profitable
D. Lower NPV and be more profitable
Answer» C. Higher NPV and be more profitable