During the month of December actual direct labour cost amounted to $39,550, the standard direct labour rate was $10 per hour and the direct labour rate variance amounted to $450 favourable. The actual direct labour hours worked were: |
A. | 3,955 hours |
B. | 4,000 hours |
C. | 3,910 hours |
D. | 4,500 hours |
Answer» B. 4,000 hours |