Q.

During the month of December actual direct labour cost amounted to $39,550, the standard direct labour rate was $10 per hour and the direct labour rate variance amounted to $450 favourable. The actual direct labour hours worked were:

A. 3,955 hours
B. 4,000 hours
C. 3,910 hours
D. 4,500 hours
Answer» B. 4,000 hours
1.5k
1
Do you find this helpful?
2

View all MCQs in

Management Accounting

Discussion

Ronald
1 year ago

Hw do you get the actual rate
0

Related MCQs