Q.

Labour Efficiency Variance is the sum total of
I)Labour Mix variance
II)Labour Cost Variance
III)Idle time Variance
IV)Labour yield variance

A. Only I and IV
B. All
C. Only II and III
D. Only I,III and IV
Answer» D. Only I,III and IV