| Q. |
In performing the works test |
| A. | the mould for test specimen should be made of non-absorbent material |
| B. | the mould should be constructed in such a way that there is leakage of water from test specimen during moulding |
| C. | the base plate of the mould should be of non-absorbent material |
| D. | all of the above |
| Answer» D. all of the above | |