Which of the following is a parallel activity? |
A. | Wall construction and carpentary work of doors |
B. | digging of foundation and construction of a well |
C. | completion of flooring and plastering of walls |
D. | completing first floor and starting second floor construction |
E. | None of the above |
Answer» A. Wall construction and carpentary work of doors |