Q.

Which of the following is incorrect with reference to work study?

A. Normal time = Representative time + Rating factor
B. Normal time = Representative time x Rating factor
C. Standard time = Normal time
D. Standard time = Normal time x Allowances
E. None of the above
Answer» B. Normal time = Representative time x Rating factor