Q.

Which of the following is normally the most appropriate sequence of events in the preparation of the indicated budgets?

A. sales budget, cash budget, production budget, budgeted balance sheet
B. sales budget, cash budget, budgeted balance sheet, production budget
C. sales budget, production budget, budgeted balance sheet, cash budget
D. sales budget, production budget, cash budget, budgeted balance sheet
Answer» D. sales budget, production budget, cash budget, budgeted balance sheet