Which of the following is an important factor that can affect the accuracy and efficacy of estimates? |
| A. | project size |
| B. | planning process |
| C. | project complexity |
| D. | degree of structural uncertainty |
| Answer» A. project size | |
| Explanation: as size increases, the interdependence among various elements of the software grows rapidly. | |