Q.

According to the time estimates made by the PERT planners, the maximum time that would be needed to complete an activity is called as                      

A. the most likely time estimate
B. optimistic time estimate
C. pessimistic time estimate
D. expected time estimate
Answer» C. pessimistic time estimate
Explanation: according to the time estimates made by the pert planners, the maximum time that would be needed to complete an activity is called the pessimistic time estimate. this estimate does not include possible effects of floods, earthquakes, etc.
2.2k
0
Do you find this helpful?
20

Discussion

No comments yet