A PERT network is activity-oriented while a CPM network is event-oriented. |
| A. | true |
| B. | false |
| Answer» B. false | |
| Explanation: a cpm network is activity- oriented while a pert network is event- oriented. event is the completion of an activity or the commencement of an activity. an event may be head event, tail event or dual role event. | |