A PERT network is activity-oriented while a CPM network is event-oriented. |
A. | true |
B. | false |
Answer» B. false | |
Explanation: a cpm network is activity- oriented while a pert network is event- oriented. event is the completion of an activity or the commencement of an activity. an event may be head event, tail event or dual role event. |