Q.

The full form of CPM is                        

A. critical path method
B. control path method
C. critical plan management
D. control path management
Answer» A. critical path method
Explanation: the full form of cpm is the critical path method. cpm networks are mainly used for those projects for which a fairly accurate estimate of time of completion can be made for each activity.