Q.

A contractor entered into an agreement with Government to construct a godown and received advance payments for the same. He did not complete the work and the Government terminated the contract.

A. The Government can claim damages
B. The Government under sec. 65 could recover the amount advanced to the contractor
C. The Government cannot claim damages
D. Both (a)&(b)
Answer» D. Both (a)&(b)
2.5k
0
Do you find this helpful?
18

Discussion

No comments yet

Related MCQs