85
74.3k

120+ Operations Management and Strategic Management Solved MCQs

These multiple-choice questions (MCQs) are designed to enhance your knowledge and understanding in the following areas: Cost Accounting .

1.

Out of the following trends in production/operations management, which one is sometimes called as agile manufacturing?

A. Re-engineering
B. Supply-Chain Management
C. Lean Production
D. Flexibility
Answer» D. Flexibility
2.

Out of the following factors that are affecting Capacity Planning, which one is Less Controllable one?

A. Machine break-downs
B. Amount of labour employed
C. Facilities installed
D. Shifts of work per day
Answer» A. Machine break-downs
3.

Which of the following stages of Product Life Cycle does attribute beginning of substantial increase in Sales and Profits?

A. Introduction
B. Growth
C. Maturity
D. Decline
Answer» B. Growth
4.

Which one is NOT an index of Productivity?

A. Man-hour output
B. Productivity ratio
C. TQM
D. Use of Financial Ratios
Answer» C. TQM
5.

The time by which an activity can be rescheduled without affecting the other activities - preceding or succeeding is called as

A. Slack
B. Independent Float
C. Free Float
D. Total Float
Answer» B. Independent Float
6.

Reliability and per unit cost of which of the following spares are less?

A. Regular spares
B. Insurance spares
C. Capital spares
D. Rotable spares
Answer» A. Regular spares
7.

The lead-time is the time:

A. To place holders for materials
B. Time of receiving materials
C. Time between receipt of material and using materials,
D. Time between placing the order and receiving the materials
Answer» D. Time between placing the order and receiving the materials
8.

The method used in scheduling a project is:

A. A schedule of break-down of orders
B. Outline master programme
C. PERT & CPM
D. Schedule for large and integrated work
Answer» C. PERT & CPM
9.

MRP stands for:

A. Material requirement planning
B. Material reordering planning
C. Material requisition procedure
D. Material recording procedure
Answer» A. Material requirement planning
10.

One of the important charts used in programme control is:

A. Material chart
B. Gantt chart
C. Route chart
D. Inspection chart
Answer» B. Gantt chart
11.

Variety reduction is generally known as:

A. Less varieties
B. Simplification
C. Reduced varieties
D. None of the above
Answer» B. Simplification
12.

Conversion of inputs into outputs is known as:

A. Application of technology
B. operations management
C. Manufacturing products
D. product
Answer» C. Manufacturing products
13.

Number of product varieties that can be manufactured in Mass production is:

A. One only
B. Two only
C. Few varieties in large volumes
D. Large varieties in small volumes
Answer» C. Few varieties in large volumes
14.

Routing and Scheduling becomes relatively complicated in

A. Job production
B. Batch production
C. Flow production
D. Mass production
Answer» B. Batch production
15.

JIT stands for

A. Just in time purchase
B. Just in time production
C. Just in time use of materials
D. Just in time order the material
Answer» B. Just in time production
16.

The first stage in production planning is:

A. Process planning
B. Factory planning
C. Operation planning
D. Layout planning
Answer» B. Factory planning
17.

Scheduling deals with:

A. Number of jobs to be done on a machine
B. Number of machine tools used to do a job
C. Different materials used in the product
D. Fixing up starting and finishing times of each operation in doing a job
Answer» D. Fixing up starting and finishing times of each operation in doing a job
18.

Example of production by disintegration is:

A. Automobile
B. Locomotive
C. Crude oil
D. Mineral water.
Answer» C. Crude oil
19.

Fixing Flow lines in production is known as :

A. Scheduling
B. Loading
C. Planning
D. Routing
Answer» D. Routing
20.

The material handling cost per unit of product in continuous production is:

A. Highest compared to other systems
B. Lower than other systems
C. Negligible
D. Cannot say.
Answer» B. Lower than other systems
21.

(Total station time/Cycle time x Number of work stations) x 100 is known as:

A. Line Efficiency
B. Line smoothness
C. Balance delay of line
D. Station efficiency
Answer» A. Line Efficiency
22.

Tempering is a process of:

A. Joining
B. Heat Treatment
C. Surface Treatment
D. Forming
Answer» B. Heat Treatment
23.

For production planning:

A. Short term forecasting is useful
B. Medium term forecasting is useful
C. Long term forecasting is useful
D. Forecasting is not useful.
Answer» A. Short term forecasting is useful
24.

Scheduling shows:

A. Total cost of production
B. Total material cost
C. Which resource should do which job and when
D. The flow line of materials
Answer» C. Which resource should do which job and when
25.

Linear Programming is a technique used for determining:

A. Production Programme
B. Plant Layout
C. Product Mix
D. Manufacturing Sequence.
Answer» C. Product Mix
26.

The effective capacity is NOT influenced by which of the following factors:

A. Forecasts of demand
B. Plant and labour efficiency
C. Subcontracting
D. None of the above
Answer» D. None of the above
27.

Key aspects in process strategy does NOT include which of the following:

A. Make or buy decisions
B. Capital intensity
C. Process flexibility
D. Packaging
Answer» D. Packaging
28.

The example of worker involvement, as a recent trend in production/operations management is

A. SCM
B. Just-in-Time
C. Quality Circle
D. MRP
Answer» C. Quality Circle
29.

Production planning in the intermediate range of time is termed as

A. Production planning.
B. Long range production planning.
C. Scheduling.
D. Aggregate planning.
Answer» D. Aggregate planning.
30.

Preventive maintenance is useful in reducing

A. Inspection Cost
B. Cost of premature replacement
C. Shutdown Cost
D. Set-up Cost of machine
Answer» C. Shutdown Cost
31.

Which one of the following standards is associated with the "Quality Assurance in Production and Installation"?

A. ISO 9001
B. ISO 9002
C. ISO 9003
D. ISO 9004
Answer» B. ISO 9002
32.

Number of product varieties that can be manufactured in Job production is:

A. Limited to one or two
B. Large varieties of products
C. One only
D. None of the above.
Answer» B. Large varieties of products
33.

In general number of product varieties that can be manufactured in Flow production is:

A. One only
B. Ten to twenty varieties
C. Large varieties
D. Five only.
Answer» A. One only
34.

Generally the size of the order for production in Job production is:

A. Small
B. Large
C. Medium
D. Very large.
Answer» A. Small
35.

Generally in continuous production the production is carried out to:

A. Customer’s order,
B. Government orders only
C. For stock and supply
D. Few rich customers.
Answer» C. For stock and supply
36.

The starting point of Production cycle is:

A. Product design
B. Production Planning,
C. Routing
D. Market research.
Answer» D. Market research.
37.

Preferred numbers are used to:

A. To determine the number of varieties that are to be manufactured
B. To the test the design of the product
C. To ascertain the quality level of the product
D. To evaluate the production cost.
Answer» A. To determine the number of varieties that are to be manufactured
38.

The act of assessing the future and make provisions for it is known as

A. Planning
B. Forecasting
C. Assessment
D. Scheduling.
Answer» B. Forecasting
39.

For a marketing manager, the sales forecast is:

A. Estimate of the amount of unit sales or a specified future period
B. Arranging the sales men to different segments of the market
C. To distribute the goods through transport to satisfy the market demand
D. To plan the sales methods.
Answer» A. Estimate of the amount of unit sales or a specified future period
40.

The time horizon selected for forecasting depends on:

A. The salability of the product
B. The selling capacity of Salesman
C. Purpose for which forecast is made
D. Time required for production cycle
Answer» C. Purpose for which forecast is made
41.

In general, medium range forecasting period will be approximately:

A. 5 to 10 Years
B. 2 to 3 days
C. 3 to 6 months
D. 10 to 20 years
Answer» C. 3 to 6 months
42.

The range of Long range forecasting period may be approximately:

A. 1 to 2 weeks
B. 2 to 3 months
C. 1 year
D. above 5 years
Answer» D. above 5 years
43.

To plan for future man power requirement:

A. Short term forecasting is used
B. Long range forecasting is used
C. Medium range forecasting is used
D. There is no need to use forecasting, as future is uncertain.
Answer» B. Long range forecasting is used
44.

Long range forecasting is useful in:

A. Plan for Research and Development
B. To Schedule jobs in Job production
C. In purchasing the material to meet the present production demand
D. To assess manpower required in the coming month.
Answer» A. Plan for Research and Development
45.

Medium range forecasting is useful in:

A. To assess the loading capacity of the machine
B. To purchase a materials for next month
C. To plan for-capacity adjustments
D. To decide whether to receive production orders or not.
Answer» C. To plan for-capacity adjustments
46.

To decide work load for men and machines:

A. Medium range forecasting is used
B. Short term forecasting is used
C. Long range forecasting is used
D. A combination of long range and medium range forecasting is used.
Answer» B. Short term forecasting is used
47.

Important factor in forecasting production is:

A. Environmental changes
B. Available capacity of machines
C. Disposable income of the consumer
D. Changes in the preference of the consumer.
Answer» B. Available capacity of machines
48.

Application of technology or process to the raw material to add use value is known as:

A. Product
B. Production
C. Application of technology
D. Combination of technology and process.
Answer» B. Production
49.

In Production by disintegration the material undergoes:

A. Change in economic value only
B. Change in physical and chemical characteristics
C. Change in technology only
D. None of the above.
Answer» B. Change in physical and chemical characteristics
50.

In Production by service, the product undergoes the changes in:

A. Shape and size of the surface
B. Shape of the surface only
C. Size of the surface only
D. Chemical and Mechanical properties.
Answer» D. Chemical and Mechanical properties.

Done Studing? Take A Test.

Great job completing your study session! Now it's time to put your knowledge to the test. Challenge yourself, see how much you've learned, and identify areas for improvement. Don’t worry, this is all part of the journey to mastery. Ready for the next step? Take a quiz to solidify what you've just studied.