…………. is an activity oriented diagram....
Q.
…………. is an activity oriented diagram.
A.
CPM
B.
PERT
C.
Histogram
D.
None of the above
Answer» A. CPM
1k
0
Do you find this helpful?
1
View all MCQs in
Principles of Management
Discussion
No comments yet
Login to comment
Related MCQs
……….is activity oriented.
…….is the disconnection of an activity before the completion of activities in a project network diagram.
Any activity which does not consume either any resource or time is called ………..activity.
An activity which must be completed before one or more other activities start is known as ……….activity.
……… is the time by which the completion of an activity can be delayed beyond its earliest finish time without affecting the earliest start time of a succeeding activity
An activity which must be completed before one or more other activities start is known as …………activity.
………. is event oriented.
The event is commonly represented by …… in network diagram
The process mapping is a ______ diagram.
Even a small production activity like loading pigs of iron into boxcars can be scientifically planned and managed. This can result in tremendous saving of human energy as well as wastage of time and materials. Which of the following Principles if management emphasize on above situation?