McqMate
Q. |
……… is the time by which the completion of an activity can be delayed beyond its earliest finish time without affecting the earliest start time of a succeeding activity |
A. | Slack |
B. | Total float |
C. | Free float |
D. | Independent float |
Answer» C. Free float |
View all MCQs in
Principles of ManagementNo comments yet