McqMate
| Q. |
……… is the time by which the completion of an activity can be delayed beyond its earliest finish time without affecting the earliest start time of a succeeding activity |
| A. | Slack |
| B. | Total float |
| C. | Free float |
| D. | Independent float |
| Answer» C. Free float | |