Q.

Forward scheduling

A. Begins with a delivery date ,then each operations is offset one at a time ,in reverse order
B. Is well suited where the supplier is usually able to meet precise delivery dates
C. Tends to minimize in process inventory
D. Assumes that procurement of material and operations start as soon as requirement are known
Answer» D. Assumes that procurement of material and operations start as soon as requirement are known