Earliest finish time can be regarded as |
| A. | Earliest start time + duration of activity |
| B. | Earliest start time duration of activity |
| C. | Latest finish time + duration of activity |
| D. | Latest finish time duration of activity |
| Answer» A. Earliest start time + duration of activity | |