McqMate
| Q. |
PERT is based on the assumption that an activity's duration follows |
| A. | Binomial Distribution |
| B. | Probability Distribution |
| C. | Uniform Distribution |
| D. | Exponential Distribution |
| Answer» B. Probability Distribution | |