Which of the following is not a reason to reduce project completion time? |
| A. | Release resources for other projects. |
| B. | Avoid penalties for late completion. |
| C. | Eliminate project critical path. |
| D. | Reduce new product development time to market. |
| Answer» C. Eliminate project critical path. | |