McqMate
| Q. |
In which of the following contract; contractor tries to complete job quickly? |
| A. | Item rate contract |
| B. | Cost plus fixed fee contract |
| C. | All in one contract |
| D. | Labour contract |
| Answer» B. Cost plus fixed fee contract | |
View all MCQs in